Leanyer Water Park – Stage 2 Works
Halikos Role: Builder for $4m Project
- Revised improved paint system to structural steel
- Project commencement and completion in 2008/2009 wet season and met client deadline for opening to the public.
- Offered DPI and alternative to manufacture inground concrete tank (80t) as precast structure off site in lieu of forming on site. This was offered as a nil cost variation which potentially saved substantial time due to works being carried out in the middle of the wet season.